How Long Does an SCE Panel Replacement Actually Take in Yucca Valley?
Longer than most homeowners expect, and almost entirely because of SCE's scheduling rather than the electrical work. The meter spot visit typically schedules one to two weeks out, then the disconnect-and-reconnect adds another two to four weeks. Mechanically it is a one-day job; on the calendar it routinely stretches to four to six weeks, and we plan temporary power around the wait.